20 Installation Guide THEIA HE-t String Inverters 357115.033, Issue 2.0, 2011 March
2.3.3.4. Jumper Position for the System Grounding Setup
The jumper above the - NEG terminal in the customer connection area monitors the
arrangement of the DC connection according to the grounding setup. When delivered, the
jumper is positioned for an ungrounded string. Depending on the requirements from the
module manufacturer, the jumper must be pulled up and positioned correctly to match the
grounding of the DC conductors.
In case of discrepancy a message will appear in the display: “Fuse fault”.
Table 2.3.1: Jumper position for the grounding setup
Connection Area
From the
side
From
above
System
Ungrounded PV String
There is no connection between
the pins.
Positive grounded PV String
The jumper short-circuits pin 1 and
pin 2.
Negative grounded PV String
The jumper short-circuits pin 2 and
pin 3.
2.3.4. AC Side (Grid) Connections
Verify that the AC grid specifications are compatible with the inverter characteristics before
connecting the inverter to the grid:
Single phase / Split phase
Voltage range (184 – 276 V)
Frequency range (50 Hz ±5 Hz)
DANGER: Ensure that the AC terminals are discharged!
Turn OFF the AC disconnector before connecting the inverter to the AC grid to
avoid shock hazards.